The Mackenzie Valley Highway has now gone through that process. It's the first project in the North on the list. But the federal shortcut does less for this road than the headlines suggest, because the Northwest Territories' own environmental review still has to finish.
News coverage says the designation is meant to streamline federal approvals and other reviews. It doesn't explain how that works.
What is the Building Canada Act?
It's one of two parts of Bill C-5, the One Canadian Economy Act, which received Royal Assent on June 26, 2025. The other part deals with internal free trade and labour mobility. The Act's stated aim is to move national-interest projects through a faster process. It says this should give companies and investors more certainty while protecting the environment and respecting Indigenous rights.
What does cabinet consider before listing a project?
Cabinet weighs a list of factors, and the list isn't closed. According to law firm Stewart McKelvey's summary, they include whether the project strengthens Canada's autonomy, resilience and security, brings economic benefits, is highly likely to succeed, advances Indigenous interests, and helps clean growth and climate goals.
Before listing a project, cabinet must also take several steps. It has to:
- Publish the project's name and description in the Canada Gazette for 30 days.
- Consult the province or territory where it will be built. If the project falls under exclusive provincial jurisdiction, it needs that government's written consent.
- Consult Indigenous peoples whose constitutional (section 35) rights could be harmed.
All of these steps are set out in the Act.
There's also a conflict-of-interest check. Before recommending a project, the minister must be satisfied that the company behind it and its directors, officers and major shareholders have not breached, and aren't facing proceedings under, the Conflict of Interest Act. Any public officials who could be in a conflict must have stepped aside.
What changes once a project is listed?
The project goes into Schedule 1 of the Act. It also goes on a public online registry that lists why it's in the national interest, detailed cost estimates and estimated timelines.
The legal effect is that the project is deemed to have favourable answers on every authorization required under the laws in a second list, Schedule 2. That list includes the Fisheries Act, the Canadian Navigable Waters Act, the Migratory Birds Convention Act, 1994, and the Species at Risk Act. The official schedule also names parts of the Canadian Environmental Protection Act, 1999, and the Canadian Energy Regulator Act, plus the Impact Assessment Act and regulations such as the Metal and Diamond Mining Effluent Regulations.
Next, the minister writes a single "Document." It lists every authorization the project would normally need, with conditions set after consulting the responsible ministers. Once issued, it substitutes for each of those authorizations. Preparing it involves a national security review of any state-owned or foreign investment, and more consultation with affected Indigenous peoples.
Listed projects also skip parts of the federal Impact Assessment Act. The planning phase doesn't apply, and neither do that Act's own timelines or its specific requirements for Indigenous consultation and detailed project descriptions. Certain decisions under the Act are deemed to be made in support of the project.
Does a designation mean the project is approved?
No. Stewart McKelvey stresses that the Act speeds authorizations up rather than eliminating them. Companies still apply for each authorization, provide the required information and pay the fees. The final Document can also come with conditions attached.
How much faster is it?
The law itself sets no time limit. The Act has no deadline for issuing the Document. The government's policy goal is a two-year approval process. There is one firm clock: a Document expires if the project hasn't started within five years of being issued. No date has been reported for when the highway's Document will be issued.
Why does the highway still need the Mackenzie Valley review board?
The Mackenzie Valley Resource Management Act isn't on Schedule 2, so the designation doesn't deem it satisfied. The highway falls under that northern regime, and it isn't on the official list of covered laws.
In an analysis for Energy Regulation Quarterly, the author argues that the Act implicitly leaves review processes set up under modern treaties unchanged. A project that triggers the Mackenzie Valley law would still have to be assessed under it. The author also concludes that, as a constitutional matter, that law can't be added to Schedule 2. That's one analyst's legal reading, not a court ruling.
So the territorial review is still the main hurdle for the highway. Its environmental assessment began in 2013, and officials expect it to wrap up by the end of 2027. If the Mackenzie Valley Environmental Impact Review Board approves it, construction could start in late 2027. How much time the federal designation saves on top of that hasn't been explained.
Has Ottawa finished consulting Indigenous communities?
Ottawa says yes, but talks are continuing. According to government sources, the federal government considers that it had "fulfilled the duty to consult" when it decided to list the highway, though Indigenous consultations will go on. Two days before the announcement, Ottawa and the N.W.T. signed a governance agreement with the Gwich'in Tribal Council, Sahtu Secretariat Incorporated and Pehdzeh Ki First Nation. Officials say a key concern raised in consultations is that easier road access could bring in more drugs and alcohol, with limited policing to deal with it.
Not everyone is satisfied on the terms. Liidlii Kue First Nation Chief Kele Antoine said permanent bridges must be fully funded if the project is truly in the national interest. Whether any group will challenge the consultation finding is unknown.
Does the designation come with money?
No. The Act says nothing about funding. Money for the highway comes from separate budget decisions. The government puts construction of the northern and southern sections at $4.2 billion, not counting the new bridges over the Great Bear, Liard and Mackenzie rivers or ongoing maintenance. Budget 2026 set aside $3.1 billion over five years. Officials couldn't say how much of the maintenance Ottawa will cover, or for how long.
The highway is also set to be the first focus of a planned federal Crown corporation for managing complex projects. That corporation has $187 million over five years, but it isn't clear when it will be up and running.
Which other projects have been formally listed?
Two projects were listed before the highway: the Pacific Link oil pipeline and a Port of Vancouver expansion, both in October 2026. BNN identifies the port project as Roberts Bank Terminal 2, which makes the highway the third.
Being sent to the federal Major Projects Office is a different step from being listed under the Act. For example, Budget 2025 proposed letting the Canada Infrastructure Bank invest in any project referred to the Major Projects Office, whether or not it's listed. So a longer list of "major projects" doesn't mean all of them carry the legal effects described above.
The order or Gazette notice that formally added the highway to Schedule 1 hasn't been cited in coverage so far, and neither has its registry entry.